Question:

For the subject solicitation, I am looking to obtain the following information:

  1. Bid documents including plans and specs
  2. Estimated Project Value
  3. Construction timeline including start/end date

Answers:

  1. Bid documents, plans, and specifications are available by registering for the bid here on the Lake County Purchasing Portal
  2. The latest engineers estimate of cost for the base bid and the alternate #1 bid is $2.7M and $4.8M respectively. 
  3. The estimated construction timeline to be substantially complete is 150 and 270 calendar days for the base bid and for the alternate #1bid, respectively. The notice to proceed is anticipated to be issued in early September.