March 16, 2021
Question:  Is there an estimated project value available for the above project?
Response:  The estimated project value is $300,000.
Question:  Is there a date of completion set yet?
Response:  The substantial completion is 90 days.
April 2, 2021
Question:  Do you have the pre-bid meeting attendance sheet for the above project?
Response:  The following vendors attended the pre-bid meeting:
Joel Avitia - Berger Excavating Contractors, Inc.
Doug Abbey - Bolder Contractors, Inc.
Nicholas Neri - John Neri Construction Co