8/17/2016
Question 1.  Please advise the type of Spray Lining that is specified for this contract.
Response:  Please reference specification sections 02957, 02958 and 02959.
8/31/2016
PLEASE NOTE THE BID OPENING DATE HAS BEEN CHANGED FROM SEPTEMBER 12, 2016 TO SEPTEMBER 16, 2016 AT 2:00 P.M. LOCAL TIME.
9/2/2016
Question 2.  Does the backfill at Section 2 need to be CLSM?  If not please provide the details on backfill.  
Response:  Yes.
Question 3.  During the shutdowns, can the work be completed 24 hours per day?
Response:  Yes, see Specification 01000 Paragraph 1.3 A. 2. 
Question 4.  With cutting in the pipe, cleaning, performing the pipe work, installing the new pipe sections… we believe the 6 outages is not enough to perform the work.  Can the outages be increased?  Is 12 outages acceptable?  
Response:  No.
Question 5.  Does the backfill for the exploratory excavation need to be tested?  If so can you provide the testing requirements?
Response:  Yes, see Specification Section 02250 for testing and compaction requirements.
Question 6. Under the unit prices, what is the difference between Item C and Item D?
Response:  Item C includes CA-7 course aggregate stone, Item D includes CA-6 course aggregate stone.
Question 7.  What are the pavement requirements?
Response:  See Specification 02500 Paragraph 3.2 C.
Question 8.  Do the joints of the pipe need to be “filled In” to before the liner is installed.
Response:  No, but per specifications the liner shall provide continuous coverage over its entire length.
Question 9.  What is the owner’s estimate on this project?
Response:  The engineers estimate is $1.38 million.
Additional Documentation:
Addendum Revised Spec Page
Pre-Bid Meeting Q & A
Revised Bid Form
Pre-Bid Meeting Sign In Sheet